GUIDE · SCOPE CHANGES

Change Order Template
for Contractors

The wall comes off and it is not what you quoted. Here is a free change order template, a filled example and the six steps that keep a scope change from becoming an argument at the final bill.

FREE TO READ · COPY-PASTE TEMPLATE · CHECKED OCTOBER 27, 2026 · GENERAL INFORMATION, NOT LEGAL ADVICE

Contractor and customer reviewing a plan on a tablet together in a half-finished kitchen remodel with exposed studs
Write the change down, price it, and get the signature before the work on the change starts.

By QuoteIron TeamUpdated 11 min read

Key takeaways

  • A change order is numbered, priced and signed before the work starts. It amends the original quote and rolls into the same final invoice.
  • It must say seven things: its own number and the job it amends, the date, what changed and why, work added, work removed as a credit, the new contract total, and the schedule effect with signatures.
  • Verbal changes fail because two people remember a driveway conversation differently. Unwritten scope creep can turn a 30% job into a 12% one.
  • Example 1 is $2,450 + $725 = $3,175. Example 2, priced from a book, is $1,850 + $455 = $2,305.
  • Issue one in six steps: stop work on the change, write and price it, show the schedule effect, send it, get both signatures, then start work.

Related: Receipt vs invoice · Net 30 vs due on receipt · How to price an electrical panel upgrade · QuoteIron help · electrician price book · plumber price book

The wall comes off, and what's behind it isn't what you quoted. Now you have a choice: eat it, argue about it later, or write it down before you touch it. A change order is the third option — a short, numbered document that says what changed, what it costs, what it does to the schedule, and that the customer agreed to all three before the work happened. This page gives you a change order template you can copy as a form or as plain text, two worked examples, and the steps to issue one.

It isn't paperwork for its own sake. It's the difference between "we discussed that" and a signature with a date on it.

Template checked October 27, 2026.

What a change order actually is

A change order amends a job you already quoted. It doesn't replace the original estimate and it isn't a second job — it's an addendum that rides along with the first one and rolls into the same final invoice. Three things make it a change order rather than a note: it's numbered, it's priced, and it's signed before the work starts.

Why "sure, I'll add it" costs you money

Verbal changes fail in one predictable way. You remember a number, the customer remembers a smaller one or no number at all, and the disagreement surfaces when you hand over the final bill and they're deciding whether to pay it. Nobody is lying. Two people just remembered a driveway conversation differently, three weeks apart.

The second cost is quieter. Scope creep that never gets written down never gets priced, and a job that was making 30% ends up making 12% because of four small "while you're here" additions nobody billed for. Writing each one down forces you to price it, which is the whole point.

The seven things a change order has to say

  1. Its own number, and the number of the job it amends. CO-2026-001 against Q-2026-047. Sequential, never reused.
  2. The date. The day it's written, not the day the work happens.
  3. What changed and why, in one plain sentence. "Feeder is aluminium, not copper as assumed." Not "additional work as discussed."
  4. What's being added, priced line by line the way you'd price anything else.
  5. What's being removed, if anything, as a credit. A change order that only ever adds looks like a shakedown; one that credits what you're no longer doing looks like arithmetic.
  6. The new contract total. Original, this change, new total. Three numbers, stacked, so nobody has to add them up.
  7. What it does to the schedule, and a signature line for both of you.
The one rule that matters: the customer signs before the work on the change starts. A change order signed afterwards is an invoice with extra steps — it has no leverage, because the work is already done and you're asking rather than agreeing.

Change order template for contractors (copy-ready)

Here is the blank form first, then the same template as plain text. Select the text, paste it into whatever you already use, and fill in the blanks. Nothing here is trade-specific.

CHANGE ORDER · Change Order No. CO-____ · Date ________

Contractor: business name, license #, phone, email
Customer: name and job address
Original job: No. Q-____ · original contract total $________ · contract date ________

What is changing and why: one plain sentence.

LineQtyPriceAmount
Work added (one row per item)__$____$____
Work removed (credit)__$____-$____
Subtotal of this change$____
Sales tax, if it applies$____
Total of this change order$____
Previous contract total$____
New contract total$____

Schedule effect: adds or removes ___ working days; new completion date ________.

Approved: Customer ______________ Date ______ · Contractor ______________ Date ______
Work on this change does not start until both signatures are on it.

Plain-text version — select, copy, paste:

CHANGE ORDER

Change Order No.:  CO-____        Date: ____________
Original job No.:  Q-____         Original contract date: ____________
Original contract total: $__________

Contractor:  [business name]  License #: [____]
             [address / phone / email]
Customer:    [name]
Job address: [address]

WHAT IS CHANGING AND WHY
  [One plain sentence: what changed, and what you found that caused it.]

WORK ADDED                                  Qty     Price     Amount
  1. [description] ......................   __     $____     $____
  2. [description] ......................   __     $____     $____

WORK REMOVED (credit)                       Qty     Price     Amount
  1. [description or "None"] ............   __     $____    -$____

PRICE OF THIS CHANGE
  Subtotal (added minus credits) ..................  $________
  Sales tax, if it applies ........................  $________
  Total of this change order ......................  $________
  Previous contract total .........................  $________
  NEW CONTRACT TOTAL ..............................  $________

SCHEDULE
  Adds / removes ___ working days. New completion date: ________

TERMS
  Billed with the final invoice. Other terms unchanged.
  Work on this change does not start until both signatures below.

APPROVED
  Customer ______________________   Date ____________
  Contractor ____________________   Date ____________

Two filled examples

Example 1, electrical. The panel upgrade is quoted at $2,450 as Q-2026-047. With the wall open, the feeder turns out to be aluminium, not copper as assumed at the walkthrough, so the change order adds a $640 feeder replacement and an $85 permit amendment. The change is $725, the new contract total is $3,175, and the schedule moves by one working day. Nothing is removed, so the credit line reads "None."

Example 2, plumbing, priced from a price book. A bathroom repipe is under contract at $1,850 (an illustrative original total). Once the wall is open, the main shutoff is a stuck gate valve and the water pressure needs a regulator. The customer also decides to skip the ice maker line. Lines below are from the QuoteIron price book at $95/hour, 30% markup, rounded up to $5; checked October 27, 2026.

LineLabor hoursPartsPrice
Added: replace main water shutoff or stuck gate valve2$45$250
Added: install or replace pressure reducing valve (PRV)2$110$335
Removed: replace ice maker supply line and valve1$25-$130
This change order ($250 + $335 - $130)$455
New contract total ($1,850 + $455)$2,305

The arithmetic for the first line: 2 hours at $95 is $190, plus $45 of parts with a 30% markup is $58.50, total $248.50, rounded up to $250.

How to issue a change order in six steps

  1. Stop work on the change. Finish what is safe and unaffected; don't touch the part that has changed.
  2. Write it down and price it. One sentence on what changed and why, then lines for added work and credits for removed work.
  3. Show the schedule effect. Days added or removed, and the new completion date.
  4. Send it to the customer. Number it, tie it to the original job, and show the previous total and the new total.
  5. Get both signatures. Customer and contractor, each dated, before the changed work begins.
  6. Start work, bill on the final invoice. Keep the signed copy with the job; the lines roll into the same bill.
How to issue a change order in six stepsStop work on the change. Write it down and price it. Show the schedule effect. Send it to the customer. Get both signatures. Start work, bill on the final invoice.1Stop work on the change2Write it down and price it3Show the schedule effect4Send it to the customer5Get both signatures6Start work, bill on the final invoice
The six steps, in order. The signature comes before the work on the change.

Change order vs revised estimate vs invoice

DocumentWhen you use itSigned?What it does
Change orderThe customer already accepted the job and the scope changesYes, before the workAmends the original job, adds or credits lines, sets a new total
Revised estimateThe customer has not accepted the original yetOnly once acceptedReplaces the earlier offer with a new price
InvoiceWork is done and you are asking for paymentNoBills the original scope and every approved change order together

Before you send it: a checklist

  • It has its own number and names the job it amends.
  • Today's date is on it, not the date of the work.
  • What changed and why fits in one plain sentence.
  • Every added line has a price; every removed line shows as a credit.
  • Previous total, this change and new total are stacked.
  • The schedule effect is in days, with a new date.
  • It says work on the change starts after signature.
  • Signature and date lines exist for both of you.
Change order example: $2,450 plus $725 equals $3,175Original contract $2,450 plus change order $725 (feeder $640, permit amendment $85) gives a new contract total of $3,175.New contract total$3,175Original contract $2,450This change order $725Replace aluminium feeder $640+Permit amendment $85+
The template’s example: an original contract of $2,450 plus a $725 change order (a $640 feeder replacement and an $85 permit amendment) makes a new total of $3,175.

Pricing the change

Price it the way you'd price the job if it walked in on its own: your labor rate, your materials markup, your normal minimum. The most common mistake is quietly discounting change work because you feel bad the estimate was wrong. The estimate wasn't wrong — the conditions changed. If you've built a flat-rate price book, most change orders are one or two templates out of it, priced in under a minute. For a sense of what an electrical change looks like, see the panel upgrade cost guide.

Don't forget the second-order costs. A change can mean another trip, another permit amendment, restocking a part you can't return, or a day of schedule you can't sell to anyone else. Those are real; put them on the line items rather than absorbing them.

“A change order signed afterwards is an invoice with extra steps.”
From this guide

What happens at invoice time

One job, one final invoice. The original scope and every approved change order land on the same bill, so the customer sees one number to pay and one balance to clear. If the job ran long enough to need money partway through, that's a progress payment against the same job, not a separate invoice — see payment terms for contractors for how the due date works, and receipt vs invoice for what to send once each payment lands.

In QuoteIron: a change order is built in as its own numbered document tied to the job it amends. It gets sent for approval like any quote, the customer signs it on their phone, and once it's approved the lines roll into the parent job's final invoice — you never bill a change order on its own. It's on both plans, free included (5 jobs a month; Pro is $15.99/month or $159.99/year), and it rides the parent job, so it never costs you an extra free job. Pick lines from 1100+ job templates. The QuoteIron vs Joist comparison shows where it sits on other apps' price lists.

Trades where this bites hardest

Anything that opens a wall, a roof or a slab. Electrical and plumbing retrofit work in older houses is the classic case — what's behind the drywall decides the price. Roofing runs on deck rot found after tear-off. HVAC changeouts turn up ductwork nobody costed. If your trade is on that list, a change order isn't occasional paperwork; it's part of the job. Questions on how it works in the app are answered in QuoteIron help.

Change order template: common questions

What is a change order in construction?

A change order is a short numbered document that amends a job you already quoted. It states what changed and why, what work is being added or removed, the new contract total, and what it does to the schedule, and it carries signatures from both the contractor and the customer. It does not replace the original estimate and it is not a second job. It rides along with the first one and rolls into the same final invoice.

What has to be on a change order?

Seven things: its own sequential number plus the number of the job it amends; the date it was written; one plain sentence saying what changed and why; the work added, priced line by line; any work removed, shown as a credit; the original contract amount, this change, and the new total stacked together; and the schedule impact with a signature line for both parties.

Does the customer have to sign a change order before the work starts?

That is the rule that makes it worth writing. A change order signed after the work is done is an invoice with extra steps: it has no leverage, because you are asking rather than agreeing. Get the signature before anyone touches the change. Requirements for enforceable contract amendments vary by state and by contract, so check your state.

Do I bill a change order separately from the original invoice?

No. One job, one final invoice. The original scope and every approved change order land on the same bill, so the customer sees one number to pay and one balance to clear. If the job runs long enough to need money partway through, take a progress payment against the same job rather than issuing a separate invoice for the change.

How should I price change-order work?

Price it the way you would price the job if it walked in on its own: your labor rate, your materials markup, your normal minimum. Do not discount change work because you feel the estimate was wrong; the conditions changed, not the estimate. Include second-order costs too: another trip, a permit amendment, a part you cannot return, a day of schedule you cannot resell.

What is the difference between a change order and a revised estimate?

A revised estimate is a new price offered before the customer has accepted anything. A change order is an amendment to a job the customer already accepted: it is numbered, tied to that job, and signed. If the customer has not yet said yes to the original, revise the estimate. If they have, write a change order.

Can I write the change order after the work is done?

You can write it, but it will not do the job of a change order. Once the work is finished the customer is no longer agreeing to a price, only deciding whether to pay one. Stop at the point where the scope changes, write it down, and get the signature first. What a late signature is worth in a dispute depends on your state and your contract.

Is a text or email approval enough instead of a signature?

Whether a text or email counts as a signed amendment depends on your state and on what your contract says about changes. A numbered change order signed on a phone, with the date on it, is the cleanest record, and it takes about as long as sending a text. If you rely on anything less, check your contract first.

General information for tradesmen, not legal advice. Contract terms, notice requirements and what counts as an enforceable amendment vary — check your state and your own contract before you rely on any template, including this one.

CHANGE ORDERS, INCLUDED

Number it, price it,
get it signed on a phone.

In QuoteIron a change order is its own numbered document tied to the job it amends — sent for approval, signed on the customer's phone, rolled into the final invoice. Free for 5 jobs a month, no card. Pro is $15.99/mo flat.

Pricing the change from a book instead of from scratch? How to build a flat-rate price book.

On the stores: App Store · Google Play

$15.99/MO FLAT · MONTH-TO-MONTH · CANCEL IN THE APP STORE OR GOOGLE PLAY, NO PHONE CALL · EXPORT YOUR DATA ANYTIME

PricingGET THE APPFAQ